Update -
We will be undergoing scheduled maintenance during this time.
Mar 31, 2025 - 21:59 UTC
Scheduled -
Continuing in our project to improve service and expand capacity in our EU region we will be performing the second phase of hardware upgrades to our edge routers in our Frankfurt datacenter.
We will be sequentially working on all edge switches. Before starting maintenance, traffic on each switch will be diverted to alternative paths.
Due to the nature of the maintenance PNI and IX BGP sessions will reset and are expected to be down for short periods as fiber connections are moved. We expect little to no interruption in ingest or web portal data flow, traffic should move to transit providers.
Mar 31, 2025 - 21:49 UTC